North Yorkshire County Council

 

Business and Environmental Services

 

Executive Members

 

24 September 2021

 

Proposed change to the Winter Service operational procedures - reductions in the salt spreading rates.

 

Report of the Assistant Director – Highways and Transportation

 

1.0         Purpose of Report

 

To enable the Corporate Director of Business and Environmental Services (BES), in consultation with the BES Executive Members, to approve

 

1.1         A reduction in some of the minimum salt spreading rates for future winter operational periods.

 

 

2.0         Background

 

2.1         In the report tabled at your meeting held on the 25 September 2020, the resolution made then was to partially reduce some of our salt spread rates, moving closer to the minimum spread rates laid out in the Government backed industry guidance published by the National Winter Service Research Group. This guidance is titled Spread Rates for Precautionary Salting, which replaced the current Well Maintained Highways – Appendix H – Section H8.

 

2.2         In the report presented on the 21 August 2020 we reported that if the move to 9g/m2 and 13g/m2 during the 2020/21 season proved successful, and our confidence in the accuracy in the gritting fleet remains high, then it will be our intention to change our operational procedures again and lower the minimum salting spread rate to 8g/m2 and the rate for road surface temperatures between minus 2 degrees and minus 5 degrees on damp roads to 12g/m2 for the 2021/22 winter season.

 

3.0         Proposal

 

3.1         Due to the experience last season of using the partially reduced spread rates, along with the confidence in gritter accuracy, coupled with the recent £2.2m purchase by North Yorkshire Highways of 18 new gritters, it is our intention, in line with the comments referred to in 2.3 above, to further reduce our proposed spread rates for precautionary salting to the minimums set out in the NSWRG guidance mentioned in 2.1 above. The rationale for determining the new reduced spread rates are shown in Appendix A.

 

3.2         The reduced salt spread rates that we are seeking approval for are shown on the proposed Decision Matrix from the draft Winter Service Manual for the 2021/22 season shown in Appendix B.

 

 

 

3.3         Whilst any definite cost saving is impossible to predict as it will depend on the prevailing weather conditions, it is expected that these reductions will save around £75k during a normal season. This is in line with our Medium Term Financial Savings strategy.

 

4.0         Equalities Implications

 

4.1       Consideration has been given to the potential for any adverse equality impacts on people with Protected Characteristics, arising from the recommendation.  The results of the impact assessment has been set out in a completed ‘decision not to undertake an Equalities Impact Assessment’ form.  This is attached at Appendix C and it shows that there are no negative impacts on any of the groups with protected characteristics.

 

5.0         Financial Implications

 

5.1       There is an estimated saving from these proposals of £75,000 in the 2021/22 and future financial years which is included in the Medium Term Financial Strategy.

 

6.0         Legal Implications

 

6.1       Section 41(1A) of the Highways Act 1980 states that a highway authority is under a duty to ensure, so far as is reasonably practicable, that safe passage along a highway is not endangered by snow or ice. Reducing our salt spreading rates to bring them into line with national guidance is not thought to weaken our response to that duty.

 

7.0         Climate Change

 

7.1       Consideration has been given to the potential for any climate impacts arising from the recommendation. It is the view of officers that the recommendation do not have an adverse on the environment of North Yorkshire and our aspiration to achieve net carbon neutrality by 2030 and a copy of the Climate change impact assessment screening form is attached as Appendix D.

 

8.0         Recommendations

 

8.1       It is recommended that:-

              i.             The Corporate Director, in consultation with the BES Executive Members agree to these reductions to the minimum salt spreading rates in our operational procedures when implementing the winter service policy.

             ii.             The Winter Service Plan and Decision Matrix are duly altered to reflect these changes.

 

 

 

BARRIE MASON

Assistant Director – Business and Environmental Services

 

Author of Report:  Richard Marr

Background Documents:     Report to Business and Environmental Services Director and Executive Members: Proposed change to the Winter Service operational procedures - reductions in the salt spreading rates and a rewording the policy to clarify our snow clearance procedures, dated 25 September 2020.


Rationale behind the revision of the NYCC salt spreading treatment matrix.

Prior to last season, the treatment matrix had been in use for many years and had not changed even though gritter spreading accuracy has greatly improved. Also, recent alterations to the guidance around salt spreading rates have convinced Officers that there was scope to reduce some of our spread rates.

 

The guidance followed comes from the National Winter Service Research Group (NWSRG), and is attached.

 

BACKGROUND TO NWSRG PRACTICAL GUIDE FOR WINTER SERVICE

The latest (2016) version of the UK Roads Liaison Group’s national code of good practice for highway maintenance matters, 'Well-managed Highway Infrastructure', no longer provides detailed guidance to practitioners regarding the delivery of the winter service.

Instead, and recognising the technical quality of its work and level of expertise residing within the NWSRG, the UK Roads Board, on behalf of the UKRLG, has requested the NWSRG to make its Practical Guide generally available to all practitioners and interested parties, as it is considered to constitute the best way of providing national best practice guidance on these issues.

 

The guidance goes into a lot of detail around the various external factors that influence how the salt that is spread works on, and is removed from, the road surface.

 

The key point of the guidance is that Authorities are to determine their own spread rate matrices that are appropriate for use on their own networks, as well as assisting them in determining which of those spread rates to utilise in response to a particular weather forecast, expected traffic and road conditions based upon this guidance.

 

The salient points to consider when determining our own matrix are:

1.            Quality of the stored salt and accuracy of the gritter fleet.

2.            Road temperatures expected during the period under consideration (usually the next 24 hours)

3.            The amount of liquid water present at the time of spreading and the following period.

4.            Traffic levels before, during and after spreading.

5.            Wind speed and direction.

6.            Residual salt present on the network.

7.            Road surfacing type.

 

Last year the Corporate Director decision recognised the new guidance but restricted any reduction in spread rates to a minimum of 9g/m2, with further reductions only to be considered after a period of monitoring and experience. As no negative impacts were observed or detected, we now propose to reduce the spread rates further in line with the national guidance.

 

NYCC proposes to further amend its treatment matrix based on the following statements:

 

1.    Quality of the stored salt and accuracy of the gritter fleet.

a)    Our salt is stored under cover and assumed to be at the optimum moisture content of 2% to 4%, and this will be checked at points through the year.

b)    The gritter fleet is modern, well maintained and calibrated at the start of every season. In season checks will be done and recorded. Therefore we will be using the rates suggested got “Good” spreader capacity.

 

2.    Road temperatures expected during the period under consideration (usually the next 24 hours)

a)    Our matrix will be divided into appropriate temperature bands.

 

3.    The amount of liquid water present at the time of spreading and the following period.

a)    Our matrix will be divided into dry, damp and wet for pre-treatments and ice, snow and freezing rain for post treatments.

 

4.    Traffic levels before, during and after spreading.

Table 8.3 in the guidance:-

The guidance states:

It is anticipated that traffic levels on the great majority of local authority road networks will fall within the ‘Medium Traffic’ category during the times periods that most precautionary salting operations are undertaken. Therefore, the recommended spread rates provided in the matrices contained within sub-section 8.6 relate to the ‘Medium Traffic’ category.

 

It is not anticipated that many local authority roads will fall into the ‘High Traffic’ category and research has shown that salt losses do not increase significantly for traffic levels beyond 250 vehicles per lane per hour, as long as this traffic is moving normally.

 

However, it is likely that some precautionary salting operations undertaken by local authorities will include routes that fall into the ‘Light Traffic’ and ‘Congested Traffic’ categories. In these situations, it is important that spread rates are modified accordingly.

 

As all out pre-treatments are on the Priority One network, our spread rates for pre-treatments will be based upon Medium Traffic levels.

Rates for post treatments do not need to consider traffic levels.

 

5.    Wind speed and direction.

The guidance states:

When treatments are carried out during high wind conditions, it is recommended that authorities monitor residual salt levels and carry out re-treatments if and where necessary. If this issue is considered to pose a significant risk, authorities may also wish to increase spread rates when carrying out precautionary salting operations during periods when forecast mean wind speeds are 20mph or higher.

 

Therefore our pre-treatment matrix for dry salting will show separate rates for when wind speeds are in excess of 20mph.

 

 

 

6.    Residual salt present on the network.

The guidance states:

Residual salt from previous operations can reduce the spread rates required to prevent frost/ice formation. However if, when decision making, residual salt levels are relied upon to reduce instructed spread rates, it is important that such decisions are evidence based. As with all other pertinent information relating to winter service decision making, the supporting data should be recorded and retained.

 

For the purposes of the treatment matrix, the effect of any residual salt has been ignored. However, further guidance is being sought from the industry.

 

7.    Road surfacing type.

The guidance asks that when spreading on porous asphalt, the spread rates provided in the guidance should be increased by 25% and the increased spread rate should be maintained for a distance of 1 kilometre ‘downstream’ of each porous section (in two-way traffic situations, the increased spread rate should be maintained for a distance of 1 kilometre at both ends of each porous section).  For other negatively textured surfaces this increase should be between 10% and 25% for the first two years of the surfacing. For the purposes of our matrix this will be covered in a foot note.

 

The recommended spread rates for dry salting in the guidance are shown below:

 

 


TREATMENT MATRIX GUIDE

 

Weather Conditions

Road Surface Conditions

Road Surface Temperature (RST)

 

 

Treatment

Salt Barn-Dry Salting (g/m2)

Dry roads only

 

Wind in excess of 20mph Salting (g/m2)

Ploughing

Forecast frost or ice, RST at or above -2oC Road dry or damp

 

 

 

8

 

 

9

 

 

No

 

Forecast frost or ice, RST at or above -2oC Road wet

 

 

 

8

 

 

 

No

Forecast frost or ice, RST between -2oC and  -3oC, Road dry or damp

 

 

 

8

 

13

 

No

Forecast frost or ice, RST between -2oC and  -3oC, Road wet

 

 

 

13

 

 

 

No

Forecast frost or ice, RST below -3oC and above -4oC Road dry or damp

 

 

 

9

 

13

 

No

Forecast frost or ice, RST below -3oC and above -4oC Road wet

 

 

 

17

 

 

 

No

Forecast frost or ice, RST below -4oC and above -5oC Road dry or damp

 

 

 

11

 

20

 

No

Forecast frost or ice, RST below -4oC and above -5oC Road wet

 

 

 

21

 

 

 

No

Forecast frost or ice, RST below -5oC and above -7oC and dry or damp road conditions

 

 

 

15

 

20

 

No

Forecast frost or ice, RST below -5oC and above -7oC Road wet

 

 

 

30

 

 

 

No

Forecast frost or ice, RST below -7oC and above -10oC Road dry

 

 

 

20

 

20

 

No

Forecast frost or ice, RST below -7oC and above -10oC Road wet

 

 

40

or (2x20)

 

40

or (2x20)

 

No

Light snow forecast (<10mm) Pre-salt

 

 

 

20

 

20

 

No

Medium/heavy snow or freezing rain forecast Pre-salt

 

40

or (2x20)

40

or (2x20)

 

No

Freezing rain falling

 

 

20

(successive)

 

20

(successive)

 

No

After freezing rain

 

 

20

20

No

Ice formed (minor accumulations)

 

Above

-5oC

20

20

No

Ice formed

At or below

 -5oC

40

 or (2x20)

40

 or (2x20)

 

No

Snow covering exceeding 30mm

 

 

20 – 40 (successive)

20 – 40 (successive)

Yes

Hard packed snow and ice

 

Above

 -8oC

20 – 40 (successive)

20 – 40 (successive)

No

Hard packed snow and ice

At or below

 -8oC

Salt/abrasive (successive)

Salt/abrasive (successive)

No

*Subject to stockpile exposure and condition and spreader capability.

Rate of spread for precautionary treatments should be adjusted to take account of residual salt or moisture

Notes:    1.  Treatments should be carried out whenever possible, after traffic has dispersed standing water.

       Successive half rate treatments may be considered where gritters return on the same route.

1.    Damp conditions definition – Water present which darkens the carriageway surface, no spray.

       Wet conditions definition – spray is evident.

2.            Porous Asphalt    When spreading on porous asphalt, the spread rates provided in the matrices should be increased by 25% and the increased spread rate should be maintained for a distance of 1 kilometre ‘downstream’ of each porous section (in two-way traffic situations, the increased spread rate should be maintained for a distance of 1 kilometre at both ends of each porous section).

 

 

The matrix from the guidance below does not account for conditions when the roads are dry and wind speeds are in excess of 20 mph. Nor do they account for porous / negative texture asphalts.

 

 


 

Initial equality impact assessment screening form

(As of October 2015 this form replaces ‘Record of decision not to carry out an EIA)

This form records an equality screening process to determine the relevance of equality to a proposal, and a decision whether or not a full EIA would be appropriate or proportionate.

 

Directorate

BES

Service area

H & T

Proposal being screened

Proposal to adjust our operational procedures within the Winter Service Policy to reduce salt spreading rates to bring them in line with revised national guidance.

Officer(s) carrying out screening

Richard Marr

What are you proposing to do?

Reduce salt spreading rates in line with national guidance

Why are you proposing this? What are the desired outcomes?

To reduce the amount of salt spread..

Does the proposal involve a significant commitment or removal of resources? Please give details.

No

Impact on people with any of the following protected characteristics as defined by the Equality Act 2010, or NYCC’s additional agreed characteristic

As part of this assessment, please consider the following questions:

·      To what extent is this service used by particular groups of people with protected characteristics?

·      Does the proposal relate to functions that previous consultation has identified as important?

·      Do different groups have different needs or experiences in the area the proposal relates to?

 

If for any characteristic it is considered that there is likely to be a significant adverse impact or you have ticked ‘Don’t know/no info available’, then a full EIA should be carried out where this is proportionate. You are advised to speak to your Equality rep for advice if you are in any doubt.

 

Protected characteristic

Yes

No

Don’t know/No info available

Age

 

ü

 

Disability

 

ü

 

Sex (Gender)

 

ü

 

Race

 

ü

 

Sexual orientation

 

ü

 

Gender reassignment

 

ü

 

Religion or belief

 

ü

 

Pregnancy or maternity

 

ü

 

Marriage or civil partnership

 

ü

 

NYCC additional characteristic

People in rural areas

 

ü

 

People on a low income

 

ü

 

Carer (unpaid family or friend)

 

ü

 

Does the proposal relate to an area where there are known inequalities/probable impacts (e.g. disabled people’s access to public transport)? Please give details.

The proposal covers the entire County

Will the proposal have a significant effect on how other organisations operate? (E.g. partners, funding criteria, etc.). Do any of these organisations support people with protected characteristics? Please explain why you have reached this conclusion.

No.

Decision (Please tick one option)

EIA not relevant or proportionate:

 

ü

Continue to full EIA:

 

Reason for decision

People with protected characteristics should not be adversely affected by the proposed changes

.

Signed (Assistant Director or equivalent):

Nigel Smith

 

Date:

10/09/21

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Climate change impact assessment                                                                                                                           

 

The purpose of this assessment is to help us understand the likely impacts of our decisions on the environment of North Yorkshire and on our aspiration to achieve net carbon neutrality by 2030, or as close to that date as possible. The intention is to mitigate negative effects and identify projects which will have positive effects.

 

This document should be completed in consultation with the supporting guidance. The final document will be published as part of the decision making process and should be written in Plain English.

 

If you have any additional queries which are not covered by the guidance please email climatechange@northyorks.gov.uk 

Please note: You may not need to undertake this assessment if your proposal will be subject to any of the following: 
 Planning Permission
 Environmental Impact Assessment
 Strategic Environmental Assessment
 
 However, you will still need to summarise your findings in in the summary section of the form below.
 
 Please contact climatechange@northyorks.gov.uk for advice.
 

 

 

 

 

 

 

 

 

 

 

 


Title of proposal

Proposed change to the Winter Service operational procedures - reductions in the salt spreading rates

Brief description of proposal

To reduce the salt spreading rates during the forthcoming winter period

Directorate

Business and Environmental Services

Service area

Highways and Transportation

Lead officer

Nigel Smith

Names and roles of other people involved in carrying out the impact assessment

Richard Marr, Area Manager, Highway Operations

Date impact assessment started

7 September 2021

 

 

 

Options appraisal

Were any other options considered in trying to achieve the aim of this project? If so, please give brief details and explain why alternative options were not progressed.

 

No other options were considered, as this proposal is a minor amendment to existing operations. Moreover, it will have a negative impact on climate change.

 

 

What impact will this proposal have on council budgets? Will it be cost neutral, have increased cost or reduce costs?

 

Please explain briefly why this will be the result, detailing estimated savings or costs where this is possible.

 

The proposal will reduce council costs as it will result in less salt being purchased for the winter service operation

 

 

 

 

 

 

How will this proposal impact on the environment?


N.B. There may be short term negative impact and longer term positive impact. Please include all potential impacts over the lifetime of a project and provide an explanation.

Positive impact

(Place a X in the box below where relevant)

No impact

(Place a X in the box below where relevant)

Negative impact

(Place a X in the box below where relevant)

Explain why will it have this effect and over what timescale?

 

Where possible/relevant please include:

·      Changes over and above business as usual

·      Evidence or measurement of effect

·      Figures for CO2e

·      Links to relevant documents

Explain how you plan to mitigate any negative impacts.

 

Explain how you plan to improve any positive outcomes as far as possible.

Minimise greenhouse gas emissions e.g. reducing emissions from travel, increasing energy efficiencies etc.

 

Emissions from travel

  X

 

 

A reduction in salt spread will result in less salt being purchased for the operation and therefore less salt transported from the mine to the highway depots.

 

 

Emissions from construction

 

  X

 

 

 

Less salt will have to be mined.

 

 

Emissions from running of buildings

 

 

 

 X

 

 

Negligible reduction from this proposal.

 

 

Other

 

 

 

 

 

 

Minimise waste: Reduce, reuse, recycle and compost e.g. reducing use of single use plastic

 

  X

 

 

 

Less salt will be spread on the highway

 

 

Reduce water consumption

 

 X

 

 

 

 

Minimise pollution (including air, land, water, light and noise)

 

 

  X

 

 

Reduced transport pollution due to less salt having to be delivered to highway depots.

 

 

Ensure resilience to the effects of climate change e.g. reducing flood risk, mitigating effects of drier, hotter summers

 

 

X

 

 

 

 

Enhance conservation and wildlife

 

 

  X

 

 

 

Marginal impact of less salt being spread

 

 

Safeguard the distinctive characteristics, features and special qualities of North Yorkshire’s landscape

 

 

 

 

X

 

 

 

 

 

Other (please state below)

 

 

 

 

 

 

 

 

Are there any recognised good practice environmental standards in relation to this proposal? If so, please detail how this proposal meets those standards.

 

  This proposal moves us to the nationally recognised minimum salt spread rates for winter operations.

 

 

 

Summary Summarise the findings of your impact assessment, including impacts, the recommendation in relation to addressing impacts, including any legal advice, and next steps. This summary should be used as part of the report to the decision maker.

 

 

As the proposal will result in less salt being spread on the County’s highway network, this proposal will have a small, but positive impact to the environment and climate change.

 

 

 

 

 

Sign off section

 

This climate change impact assessment was completed by:

 

Name

Richard Marr

Job title

Area Manager

Service area

Highways and Transportation

Directorate

Business and Environmental Services

Signature

Completion date

7 September 2021

 

Authorised by relevant Assistant Director (signature):

 

Date: